DOCKSIDE ROAD / SMITHS DOCK ROAD, SOUTH BANK
Major works will be in operation on 2nd February 2019 for up to 6 months for service diversions and construction of new roundabout. Works to be carried out by Hall Construction Services Ltd (Enquiries: 01740650500 or 07970 497873)
BROADWAY, GRANGETOWN
A temporary lane closure will be in operation on the 1stMay 2019 for 3 weeks to install new electrical cable. Works to be carried out by O’Connor’s on behalf Northern Powergrid enquiries: 07799658660
NORMANBY ROAD, ORMESBY
Two-way temporary traffic signals will be in operation from 23rd April 2019 for up to 4 weeks to install a new electricity main and transfer supplies. Works to be carried out by Freedom on behalf Northern Powergrid (In case of signals failure: 07824 540196)
TRUNK ROAD, REDCAR (STEEL HOUSE R’bout to KIRKLEATHAM LANE)
Intermittent temporary lane closures will be in operation on the 23rd April 2019 for 6 weeks for new gas main. Works to be carried out by Northern Gas Networks (Enquiries 07880008107)
LONGBECK INDUSTRIAL ESTATE, MARSKE
Temporary road closures for the whole estate will be in operation from the 29th April 2019 for 2 weeks to resurface carriageway. Works to be carried out by Redcar and Cleveland Borough Council (Enquiries 01642 774774)
SKELTON AND BROTTON BYPASS
An overnight road closure (between 19:00 and 6:00) will be in operation from the 7th May 2019 for 1 week to resurface the carriageway. Works to be carried out by Redcar and Cleveland Borough Council (Enquiries 01642 774774)
WESTGATE ROAD / REID TERRACE, GUISBOROUGH
Multi-way temporary traffic signals will be in operation from 2nd April 2019 for up to 8 weeks to install a new electricity main and transfer supplies. Works to be carried out by Clancy Docwa on behalf Northern Powergrid (In case of signals failure: 07498476324)
A173 NEWTON UNDER ROSEBERRY TO BOROUGH BOUNDARY, GUISBOROUGH
Two-way temporary traffic signals will be in operation from 2nd May 2019 for up to 1 week to locate faulted cable section and repair. Works to be carried out by Northern Powergrid (In case of signals failure: 07545 701482)
SMEATHORNS ROAD, STANGHOW
Two-way temporary traffic signals will be in operation from 15th May 2019 for up to 1 day for safety for Engineer to work in Underground structure. Works to be carried out by BT (In case of signals failure: 07710018581)